Suppose a finished product is put PIRs through MD61 and run MRP , dependent requirements are generated for the BOM child parts of the finished product .
Latter when I do planning for the same finished product subsequently for the next time periods ,through MD61 , ,,,,what is happening is though I am deleting the existing planned orders of the finished product , dependent requirements of the child parts are still remaining ,not getting deleted automatically , because of which system is considering these dependent req as demand and generating procurement proposals for these old dep req quantities also .
How to avoid these ?
How to delete the existing , unused PIRs ?through MD75/76??
How to delete the existing ,unserviced planned orders ?through MD16?
Most importantly how to delete the dependent requirements of the child parts ? or how to set the system not to consider these old /existing dep requirements for generating procurement proposals during MRP run ?
Please provide necessary inputs
Madhu Kiran