Hi Experts,

Just a quick question. As I searched MOPZ in solman has been retired and replaced by SAP MAINTENANCE PLANNER since that's the case, I don't need SOLMAN anymore when upgrading/updating SAP Systems like SAP ECC 6.0 ?


10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Bartosz Jarkowski Jan 11 at 10:02 AM

It's difficult to give a single answer to your question :)

You are correct - maintenance planner is now the tool to calculate the upgrade queue, however, you need to upload your system data somehow to SAP. You have two options here:

SAP recommends using Solution Manager to upload the data, as it makes more checks during the queue calculation. I have used the second option once and unfortunately some packages were not included in the queue, however, I don't know if they would be included if I used the correct procedure.

I hope this answers your question :)