MTO COGS GL Account as cost component - Urgent

former_member1278276
Participant
0 Kudos

Dear CO Experts,

We have MTO and intercompany Costing scenario, Material A is produced in Plant X and Transferred to Plant Y. In Plant Y CIR ( Customer independent request is created) is Costed, while doing CIR/Sales order costing in Plant Y for material A, system is asking to assign COGS GL account in OKTZ. As far as i know COGS GL account should not assigned as cost component. Plant Y doesn't have any BOM or routing for Material A. This is urgent as we have planned go live tommorrow.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member259539
Active Participant
0 Kudos

Dear Santosh,

Please check Procurement type in MRP2 view of material master in MM02. it should be procurement type E for in house production.