Skip to Content

Need - Settings of Target Client for BDLS execution after Hom System Copy

Dear All,

I have performed a homogeneous client copy.

Can someone help me with the settings of the target client necessary, to run the BDLS.

Also, guide me about the entries to be made in BDLS screen.

Thanks and Best Regards,

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on May 01, 2008 at 12:41 PM

    Hi Prashant

    Refer SAP not number 325470 and 121163 for information you need.

    Although notes are for BW systems. Will help you in the process.

    Hope this helps.

    Regards

    Rahul

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Rahul,

      It was reallly a helpful answer.But yes, there are still few things which we are still looking for an answer for.

      What are the necessary client settings for executing BDLS in the target client.

      Also, can we execute BDLS multiple times if things are not converted in one time.

      Like if we execute the BDLS once w/o opening the client, then what can be done thereafter

      ( guess this is actual problem)

      Just to answer your query, the system is SAP Netweaver 2004s SR2

      Thanks and Regards

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.