MRP requirement queries

Hello,

My apologies if I have posted this in the wrong place. Our business requires that MRP be implemented. Business head has the following queries:

1. Minimum 45 days stock should remain in the system. Where in the system 45 days stock should be maintained material wise? Can required stock level be set from material master?

2. How to handle three months lead time in MRP for imports, given that 45 days stock needs to be maintained at all times.

3. Enter requirements for one year in MRP, but only requirements for first three months should be changeable, rest should be restricted. Is this possible at the authorization level or is there another way? Is this even possible?

Any responses to the above queries will be greatly appreciated. Thanks.

Regards,

Khan

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on May 01, 2008 at 04:19 PM

    Hi Khan,

    Please post this query under Forum: SCM - PP,i believe this will give you the right solution.

    /N

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 01, 2008 at 08:34 PM

    1. Minimum 45 days stock should remain in the system. Where in the system 45 days stock should be maintained material wise? Can required stock level be set from material master?

    if you are using the reorder planning than you can maintian the reorder point as 45 days stock and maintina maximum stock level so when you run MRP system will chek this two parameter and generates the requirement accordingly

    2. How to handle three months lead time in MRP for imports, given that 45 days stock needs to be maintained at all times.

    Tyy with above combination with planned delivery time as 90 days.

    If you have APO than you can handle this scenario very well

    3. Enter requirements for one year in MRP, but only requirements for first three months should be changeable, rest should be restricted. Is this possible at the authorization level or is there another way? Is this even possible?

    This can be handle via APO.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.