Evaluations for Actual Cost and Revenues

Hi all,

Is there any way we can bring Actual Costs and Actual Revenues from the Internal Orders to Evaluations report?

The standard evaluations dont seem to provide the same.

Any suggestions/help would be appreciated.

Regards,

Vivek Pandey

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    May 07, 2008 at 01:43 PM

    I have not tried bringing these fields into custom evaluations but the initial home page of cProjects has these columns. Values for these column are derived based on extract layout 0_Dashboard. "Use Dashboard" property shld be checked if the project need to appear in this initial project dashboard screen.

    Thanks

    Pugazh

    Add comment
    10|10000 characters needed characters exceeded

  • May 07, 2008 at 03:33 PM

    Hi Vivek,

    I think, the main pre-requisiton is that the involved project is linked with the internal order using FI integration. Check the tab 'accounting' if such link exits or not.

    Kind regards,

    Zhenbo

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Zhenbo,

      We've already set up accounting integration using internal orders.

      Regards,