Problem While Executing T.CODE DP90

Hi,

We have Upgrade our system from 4.6C to ECC6.

We are facing following problem while executing Resource Related Billing request

Through Transaction code DP90.

Process.

1. We are creating Sales Order and system will create Service order automatically as per the configuration.

2. In service order we have External as well internal operations ,

Internal operations will be confirmed through IW41, and External Operations we are creating Purchase Requisition then creating PO and MIRO,

After all Operations confirmed we will make Service order status as technically completed, then we are executing DP90 for Resource Related Billing, System will determine the material, combination of Cost element and Activity Type (Which is configured in T.Code ODP1) For External Operations System is Considering Activity Type for material determination in 4.6c but it is not considering Activity Type for Material Determination in ECC6 for External Operations.

Please Help me,

Edited by: D B on Apr 29, 2008 6:13 PM

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Apr 30, 2008 at 04:59 AM

    Hello,

    Check the activity types are valid in the current period or not...

    Prase

    Add comment
    10|10000 characters needed characters exceeded

    • HI,

      Problem is resolved; we are using one user exit for external operations which is not activated because of that we are getting this problem, now we activated that.

  • May 01, 2008 at 03:10 PM

    HI,

    Problem is resolved; we are using one user exit for external operations which is not activated because of that we are getting this problem, now we activated that.

    Add comment