Hello,

There is a batch job at our end that creates PO from PR. But after observing in EKKO i got to see that most of the POs are created manually. just a couple of tehm are created by batch job.

I've checked the materials and vendors of the PO which were creaated manually both the places had 'Auto PO' box checked. Moreover all the PR's had a source of supply.

Please help me out why the batch job did not create almost all the POs?

Thanks,

Amit

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member210560
Active Contributor
0 Kudos

Dear Amit,

You can use report RM06ME59 for release 5 or report RM06ME59_4_6 (rel 4 to 4.7)

to check this out. The report was provided in SAP Note 786303.

Hope this help,

Ian

Former Member
0 Kudos

Lakshman has explained

you need to have the source list setup (make sure info record exist) or contract is exist and it is assgned to the source list

but as per your email the source is determined in the PR that means source are setup properly

now check the variant of your back ground program of AutoPO

if the variant is not matching with your PR's than it will not creates the PO

so create few PR's and test it with ME59N with the background job variant and see how it is going

some time in the variant let say you have setup the release date but if it is not matching with PR release date than it will not create the PO

so in short you need to test same varinat online than setup for back ground.

Former Member
0 Kudos

Just the source of supply is not enough. Was there a info record or a contract maintained for the material and vendor? Also, was this info-record or contract assigned to in the PR or a source list maintained?

Regards,