Query on Planning Startegy

PP Gurus,

Header Material - A

Component – B

Business wants to plan Component B by PIR. This PIR should get consumed against requirement of Header Material – A from Sales Order. Which planning strategy should be used? Please guide.

Thanks in advance.

Regards,
Upendra

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 11 at 06:35 AM

    Dear,


    Use Strategy 40


    Below document will help you understand Strategy 40

    https://help.sap.com/viewer/dae616f6ebf842de8ccc4d9824bbc755/6.00.29/en-US/3923bf53d25ab64ce10000000a174cb4.html

    Thanks

    Add comment