Query on Planning Startegy

Former Member
0 Kudos

PP Gurus,

Header Material - A

Component – B

Business wants to plan Component B by PIR. This PIR should get consumed against requirement of Header Material – A from Sales Order. Which planning strategy should be used? Please guide.

Thanks in advance.

Regards,
Upendra

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Dear,


Use Strategy 40


Below document will help you understand Strategy 40

https://help.sap.com/viewer/dae616f6ebf842de8ccc4d9824bbc755/6.00.29/en-US/3923bf53d25ab64ce10000000...

Thanks