Hi all,

Please read below

I created work order for 10 pcs .

Out of which 4 pcs got scrap during operation so during Co11n, I confirmed yield as 6 pcs and scrap as 4 pcs.

Next I received goods in MB31 i.e all 10 pcs in good storage location. Now i posted those 4 pcs from good storage location to scrap storage location using 311(mvt type)

Next i posted MB1A - 551 those 4 pcs from scrap storage location for scrapping.

Please explain if this is the correct process ?

What is the effect of confirming 4 pcs as scrap during co11n?

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Apr 28, 2008 at 06:33 AM

    hi

    Scrap in confirmation means extra 4 pcs from the components (261 mvt )will be consumed from stock.Its better to automate GR in confirmation

    reward if useful

    Amit

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 28, 2008 at 06:39 AM

    hi

    this is wirte process .that is no effect.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 28, 2008 at 10:07 AM

    ok

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.