on 04-28-2008 7:27 AM
Please confirm what is the validity periods in terms of transaction ME21N,
does it mean begin of validity period means the starting of date from which vendor needs to be paid and end of validity period
means from tille whcih dsate we can pay to the vendor
in whcih table we maiantain the valdity dates.
does document date with ME21N have any significance related with valdity period dates
Hi
Start of Validity Period
Date as of which services can be performed or materials delivered.
In the case of outline agreements:
Start of the stipulated validity period of an outline agreement.
In the case of RFQs:
Start of the period in which the quotation is to be submitted.
In the case of purchase orders:
Start of the period in which the service is to be performed or the material delivered.
Service entry sheets can only be created within the specified period.
End of Validity Period
Date up to which services can be performed or materials delivered.
In the case of outline agreements:
End of the stipulated validity period of the agreement.
In the case of RFQs:
End of the period in which the quotation is to be submitted.
In the case of POs:
End of the period in which the service is to be performed or the material delivered.
No further service entry sheets can be created after this date.
Thanks & Regards
kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Validity date in PO means ,life of the document
validity start date means you do the GR only on that date or before validity end date , after the validity end date you cannot do the GR,that means validity of the document end.
For frame work order document type FO you will have validity start date and end date in sap standard.
Reward if helpful
Regards
venu gopal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi veenu,
Iam not aware of term GR, please answer my question
does validity period indicates the interval in which org needs to make a payment to the vendor .
does the document date have a relation with validity periods.
in the EKKO table what arethe fileds which corresspond to validity period.