Hi,

MRP not generating planned orders

In material Master planning strategy 11, MTS, GRP are maintained. While creating PIR Req Type is maintained as Type BSF,

On the screen it prompts Warning Message:

Material Not Maintained for GRP, but Ind Req are created with BSF as MRP element Type.

When mrp is run planned orders are not generated??????

If PIR is given in the year 2009, system generates planned orders..

We do not have any stock, or any dep requirments

Can anyone guide me in this regard

Tks and Regards

Murali

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Please give the message class and number.

Ram

Former Member
0 Kudos

hi ramu,

Message no. 6P053

murali

former_member335796
Active Contributor
0 Kudos

Hi,

The Message says " Errors occurred while reading data -> error log"

Did you get any error log? Please provide the error log..

Regards,

Siva

Former Member
0 Kudos

hi shiva,

the error log is

requirment type grp does not exists for the material

murali

Former Member
0 Kudos

Hi,

pls check in MD61 - Requirement parameters screen - whether the version active at the bottom of the screen is checked.

former_member335796
Active Contributor
0 Kudos

Hi,

Check the below:

1. Pl. Strategy : 11

2. Mixed MRP Indicator : 2

3. For Strategy 11, Req. type: BSF, Req. Class :102.

4. Strategy Group :11, whether the Strategy :11 is maintained in that??

Revert for further discussion..

Regards,

Siva

Former Member
0 Kudos

hi,

R u running MRP for top level material having planning strategy 11 and mixed MRP = GRP.

Amit

Former Member
0 Kudos

hi siva,

done exactly as per ur suggestion,

but the same problem persists

murali

Former Member
0 Kudos

hi abdullah,

i have maintained active version

murali

Former Member
0 Kudos

hi amit,

I am running running MRP for top level material having planning strategy 11 and mixed MRP = GRP.

murali

csaba_szommer
Active Contributor
0 Kudos

Hi Murali,

After material master settings please delete all the records in MD62 and recreate them - just a suggestion.

BR

Csaba

Former Member
0 Kudos

hi csaba,

i have deleted all using md62

and even i tried with new material, which i have created only to test

murali

Former Member
0 Kudos

hi

Check whether PIR is created with active version and req type BSF

Check the planning file entrt in MD21

Reward if useful

Amit

Former Member
0 Kudos

hi,

planning file exits but same problem exists

murali

Former Member
0 Kudos

hi

Check MRp type : PD

Check matreial status in MRP1

Check discontinuation indicator :should be blank

Amit

Former Member
0 Kudos

hi amit,

it is blank only

murali

Former Member
0 Kudos

hi, just go through this sheet,

http://help.sap.com/saphelp_47x200/helpdata/en/38/1a37e58ccd11d1918c0000e8a5f6e6/content.htm

see the sample scenario, & maintain MRP Type PD.

regards,

Anant...

Edited by: anant joshi on Apr 28, 2008 12:49 PM

Edited by: anant joshi on Apr 28, 2008 12:51 PM

Former Member
0 Kudos

hi,

there is problemw with variant creation for year 2008, it has been sorted by our techinical team.

tks

points are rewarded

murali

Answers (3)

Answers (3)

former_member335796
Active Contributor
0 Kudos

Hi,

Pl. check your SAP System date with Basis.

Regards,

Siva

Former Member
0 Kudos

HI,

While Creating PIR (MD61), You can set the parameter BSF, and select version "00' for requirement plan ans save it, then enter the PIR save it.

Regards

E.Rambabu

Former Member
0 Kudos

I met the same proplem before which was arisen by the wrong MRP type which was filled with M0. After changing to PD,It's OK. or You can MD42 to test that.so many friends've given kind reply ,pls tell us the current status,thanks!

shining

Former Member
0 Kudos

hi guys,

when requirments are in 2009 year planned orders are getting generated, but not in year 2008?????

murali

former_member335796
Active Contributor
0 Kudos

Hi,

If you want to use the Planning Strategy 11, then you should maintain the Mixed MRP Indicator in MRP-3 View as 2 (Gross Requirements Planning).

Try with this and revrt for further discussion..

Regards,

Siva

Former Member
0 Kudos

hi shiva,

not generating planned orders, same problem persists