HELLO
When I am running time evaluation using TM01 upto 31.03.2009 system is showing error saying that "no work center data on 18.02.2008"
He has been hired on 25/2/2008 and all data is maintained from 25/2/2008. The PDC recalculation date in IT3 was set as 18/2/2008 and i changed it to 25/2/2008.
Kindly help me out how to resolve this error as i am not able to generate absence quota for this Employee.
warm regards
Subramanyam T N