Hi,

if in a production order there are some tasks - there may be some changes in the number of products that have been finished - eg due to some crashes while manufacturing is done. As an example it might look like

production order 100 task 10 100 ea

production order 100 task 20 80 ea

production order 100 task 30 80 ea

production order 100 task 40 70 ea

After each task the output should be confirmed - one should know how many intermediate products have been manufactured.

Is there any way to do this? This is very important when using external resources...

Kind regards,

Klaus

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

0 Answers