Scheduling of pld. order incl. production versions

we are running production versions controlled by quote arragements. Because of the different routers in the background of the production versions we generate different InHouse production times. Currently we established the longest Inhouse prod. time as default in MM.

In some cases the basic dates of a pld. order deviate from the productions dates. I have the impression that the basic dates are driven by the InHouse production time out of the MM, the production dates are driven by the router.

My question is, is there a possibility to switch the basic dates always to the router or to synchronise them with the production dates ?

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 24, 2008 at 12:50 PM

    Hi,

    The basic dates are calculated based on the in house production times and the production dates are calculated from the times given in the routing.

    In SPRO tcode OPU5 you can synchronise that basic dates

    are adjusted with production dates.

    Regards,

    nandha

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 24, 2008 at 06:48 PM

    In OPU5, under Adjust scheduling level section, change the adjust dates

    from

    "Adjust basic dates,adjust dependent requirements to operation dates"

    to

    "Do not adjust basic dates,dependent requirements to operation dates"

    With the above configuration change, the production dates will the same as Basic start dates

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      thanks for your replay,

      these setting in OPU5 synchronized the basic start date. But I have still the following effect,

      Scenario,

      -two routers for one material number,

      -router one 100 days inhouse production time,

      -router two 30 days inhaouse production time.

      -router one with 100 days inhouse production time, set as default in material master

      -quote arrangement with 50% deployment

      -demands above 30 below 100 days

      Effect,

      system splitts between versions acc. quota arrangement and sets all pld. orders to forward scheduling incl. the ones which have only 30 inhouse production time. Because we are starting the 30 day pld. orders to early.

      Is there a way to change backswards / forwards scheduling depending on the production dates ?

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.