on 04-22-2008 4:08 PM
Hi pal's,
I need to Recieve Goods at no price.
After a lab analisys i can determine the price i'll pay for those goods.
How can i made it?
Thanks.
hi buddy
i havent try this but u can try
make a po for material as free goods
then do the gr ,this gr will be zero cost
then change po with price
then do miro
but in this case the valuation may not take in migo
just try this and let me know weather it worked /not
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi buddy
i havent try this but u can try
make a po for material as free goods
then do the gr ,this gr will be zero cost
then change po with price
then do miro
but in this case the valuation may not take in migo
just try this
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
if the amterial is using moving average price control indicator then u can do that as u r planning
create the po for non valuated good reciept and then post the invoice via miro
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.