Hi guys,

I was creating a Pipeline process with materials

during that process i encountered a error in material movement

(MB1A). the error is i never created a cost center,

so it asks for a cost center..

How to create a cost center?

can anyone please tell me the process for rectifying my error

Regards

Jino

Accepted Solutions (0)

Answers (3)

Answers (3)

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

You can configure cost center for your pipeline procurement and the steps are:

OKKP: Create Standard Hierarchy for Cost Centers,

KA01: Create Cost Element,

KS01: Create Cost Center,

Also check Field Status Variant and Posting Period Variant in OBY6 before rising PO and posting GR & GI.

Regards,

Biju K

Edited by: Bijay Kumar Barik on Apr 23, 2008 8:05 AM

Former Member
0 Kudos

Hi

Go to T.code KS01

Create a cost center external assignement so you casn give any name. Such as Pipeline.

Give the valid from

Give the mandatory details & save the cost center.

Please follow the link for more details

http://help.sap.com/saphelp_erp2004/helpdata/EN/08/51457e43b511d182b30000e829fbfe/content.htm

Use the cost center in the Pipe line consumption

Thansk & regards

Kishore