on 04-22-2008 3:17 PM
Hi guys,
I was creating a Pipeline process with materials
during that process i encountered a error in material movement
(MB1A). the error is i never created a cost center,
so it asks for a cost center..
How to create a cost center?
can anyone please tell me the process for rectifying my error
Regards
Jino
Hi,
You can configure cost center for your pipeline procurement and the steps are:
OKKP: Create Standard Hierarchy for Cost Centers,
KA01: Create Cost Element,
KS01: Create Cost Center,
Also check Field Status Variant and Posting Period Variant in OBY6 before rising PO and posting GR & GI.
Regards,
Biju K
Edited by: Bijay Kumar Barik on Apr 23, 2008 8:05 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Go to T.code KS01
Create a cost center external assignement so you casn give any name. Such as Pipeline.
Give the valid from
Give the mandatory details & save the cost center.
Please follow the link for more details
http://help.sap.com/saphelp_erp2004/helpdata/EN/08/51457e43b511d182b30000e829fbfe/content.htm
Use the cost center in the Pipe line consumption
Thansk & regards
Kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This doc should help you create a cost center.
http://www.copacustomhelp.state.pa.us/infopak/nav/finance/controlling/file1417/index.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.