AVOID CONSOLIDATION OF PURCHASE REQUISITION AGAINST MRP RUN

Dear sir

In a system right now PR has been consolidating for same material same plant same order same date. But for end to end tracing actually if this condition is there (Consolidated PR for same material same plant same order same date) then i cannot differentiate against the same.

If in a day we are creating sales order no 11110000 with the material ABC with 2 schedule line for same date on same plant then PR has to be created twice against the same.

In a Short - We have Requirement of to avoid the consolidated PR's

Please suggest which area we have to work for this

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 05 at 04:15 PM

    Hello

    It is a standard MRP behavior to create a single purchase requisition for requirements in the same day. The following blog post explains how to use a BAdI as a workaround to create separated requisitions, but I have never tested it:

    https://blogs.sap.com/2014/09/10/how-to-create-separate-planned-order-purchase-requesition-for-same-date/

    Regards,

    Caetano