Dear all,

I have created a subcontracting PO. Migo is done and the finished assembly material is subject to quality management. When I am posting a return delivery of the finihed product in QA11 or QA32 , system gives the error message no LB 031

" Of the required qty of materials quantity will remain open"

Regards.

Milind

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Please check the settings for Subcontract order with respect to delivery type. This is the place where we assign the Plant to Delivery type. Please let me know if you are still having problems.