Hi Experts,
I have 3 RMs..2 are used in Setup activities and one is in production.
When I run Production planning run, sytem is generating Purchase Requsition for RMs which are used in Set-up but No PR is generated for the RM which is used in Production. (Dependent demand is generated )
I have run SAP_PP_001, SAP_MRP_001 and SAP_MRP_002 heuristics in sequence.
Please help.
Thanks,
Vipul