Full accept or Rejection of stock posting is available from Inspection lot.Is it possible partially accept or reject of stock at HU level or without HU from Inspection lot in incoming Inspection, If EWM is activated for that storage location.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jan 04 at 03:26 PM

    HU has a lot of quirks to it. QM does work with HU. But you cannot do a partial posting of an HU as far as I know.

    I believe, if you have two or more HU's assigned to an inspection lot, and they are the top level HU's, you can post/reject those HU's independent of each other. But you can't split an HU in QM. Having EWM also puts another wrinkle into the process. I'm not familiar enough with EWM to give you a definitive answer but last I worked with it, EWM had a number of limitations with working with QM and it seemed only the most standard processes were supported.

    Don't be surprised to find you won't find a lot of "experts" with experience in HU's with EWM.

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 08 at 10:34 AM

    Hi,

    It is possible to do Partial release for EWM - QM integration in S/4 Hana 1610.

    You need to implement SAP Note 1953900 and Badi "QEVA_SUBSCREEN_1101"

    Regards,

    Vivek

    Add comment
    10|10000 characters needed characters exceeded

    • Does that allow you to do a partial posting on quantities within an HU?

      Since HU's can be nested, this can be a very difficult undertaking. Are their limitations on the note? How many levels of HU's can you process this way?