Skip to Content
avatar image
Former Member

Different work centers in Service Order

Hi.

While creating a Service Order in IW31, I see a different Work Center and plant from the one in sub-screen First Operations, (PC-REP/ 1200) and the TL (1410) is getting determined accordingly/ automatically. When i change the WC in that sub-screen to PC-SERV/ 1000, the TL remains the same (as expected) but in the Operations tab only the work center of the first line item changes, the other line items remain PC-REP/1200.

Can you please guide me for the correction of the same so that this descrepency could be removed. I am an SD consultant trying to run a CS cycle. I would be grateful if you could spend some time and guide me.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jan 04 at 12:16 PM

    Hi,

    You have tag this question to the production planning and this question is not really a PP issue. you need to tag it to >>

    PLM Enterprise Asset Management (EAM)/Plant Maintenance (PM)

    In my knowledge it is fetching the work center from the functional location but PM guy will guide you better.

    Regards,

    Solomon

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 09 at 08:11 AM

    SAP Light,

    There is no standard functionality that replicate a work centre change down the operatoin list.

    PeteA