Hi,

Our company is planning an upgrade from R/3 4.7 to ECC 6.0.

Do we have to implement SAP Solution Manager ? What is the added value of SAP Solution Manager besides the acquisition of support packages and OSS notes ? Monitoring is also a feature but I'm doing this from the RZ20 (CCMS) and it works fine (for our small system landscape with only two systems, DEV and PRD).

If the SAP Solution Manager is a 'must do', do we have to install it on a separate host (meaning additional hardware and maintenance costs) or are there other solutions ?

Thanks in advance,

Erik

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

During upgrade you need to provide Solution Manager Keykey which can be generated only on Solution Manager.

Check SAP Note : 805390 and the related notes on how to generate the Key

You need execute to SMSY and provide the System Id/ System No/ Msg Server Host

Its would be better to Install Soluiton Manager on a seperate Host.

Check this link for more clarifications :

https://www.sdn.sap.com/irj/sdn/docs?rid=/library/uuid/ce68fda1-0c01-0010-f88b-f5fc4e9d78bb

Edited by: Shaji Jacob on Apr 21, 2008 9:27 PM

Former Member
0 Kudos

Thank you very much for the information, this clarifies a lot to me.

Kinds regards,

Erik