on 04-21-2008 8:27 PM
Dear All,
Whenever the user enters the document, if the amount exceeds the budget amount, the system will send the mail to the concerned person.
Where do customize the settings for sending the mail?
Please reply - very urgent...
Regards,
Ranesh
SPRO--> Internal Order ---> Budgeting and Availability control --> Maintain Budget Manager.
Maintain Budget Manager
In this IMG activity you specify the budget managers responsible for your
different order types.
When defining the tolerance limits for a budget profile, you can also
specify that a message is to be sent automatically to the budget manager
if the funds allotted exceed the tolerances defined.
This message names the order in question and the business transaction
that triggered the action. In addition, you are also informed of the
level of overrun or underusage, as well as the document number.
The budget manager can also call up the relevant cost report directly
from the message.
If there is no budget manager defined for a particular order type, the
system issues an error message instead of a mail and warning message.
You can define a budget manager for each controlling area, order type,
and object class.
Examples
COA Type ObjCl User name
0001 0100 INVST User1
0001 0100 GKOST User2
0001 0100 * User3
0001 * INVST User4
0001 0200 INVST User5
0001 * * User6
In orders with controlling area 0001, order type 0100, and object class
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.