Hi guys
I created workcenters, routing, bom, control cycle record and prod. verison for the material before creating the Prod. order. Now, I am neither able to see the Pick List nor Material Staging (Simulation) after releasing my Prod. Order. The exact error is "No WM relevant components exist". All my materials are warehouse managed.
Hope to hear from you.
Regards,
Vikas
Hi
you are mentiuoning that control cycle .
Have assigned the coponents to the storage location which is assigned to ware house.
pl. chk this.
Regards
YMREDDY