on 04-21-2008 7:05 PM
Hi,
What is the setting to pick up the scheduling data from routing operation data when a production order is created?
Thanks
Ramakanth
Transaction OPU3 gives the scheduling parameters for production orders.
Regards,
Saravana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramakanth,
Scheduling parameters are specified in T.Code : OPU3.
We specify the type of scheduling ( Detailed scheduling, rate-based scheduling, Rough cut scheduling etc,)
regrads
Ram Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.