Internal Order - Budgeting

former_member1346673
Participant
0 Kudos

Dear All,

We are having the scenario that we need to allocate budget for internal orders. Meanwhile we need to allocate the budget amount for cost element as planning based on the internal order. But both amount are not same.

For e.g.,

Internal order Budget (KO22) may have USD 40,000.

Cost element planning (KO12) based on the internal order may have USD 20,000

During the document entry, the user wants to get the Error or Warning message when the budget exceeds based on the relationship between Internal Order and Cost Element.

How do I bring the scenario?

I request you to all, please reply.

Regards,

Ranesh.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Set the tolerance limit, level at 3 (Availability control) for internal order.

Rgds

Aman

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

Create a budget profile at OKOB, the define tolerence limits for this profile using the node below:

Controlling> Internal Orders> Budgeting and Availability Control--> Define Tolerance Limits for Availability Control

And once this is done, assign it to the Internal order type in KOT2_OPA.

When you set the tolerance limits you can specify the requirements that you mentioned

assign points if useful

regards

srilakshmi