Hello SAP Folks,
From the V_V2 report, we are trying to use it and extract few details like the line items for which the rescheduling happened.
Because the report contains lots of information, when it is downloaded as an Excel file, you cannot use filters and extract the data you need. If an order line item schedule line date is changed, it is represented in report as 2 line items.
So, we are struggling to find a way to report the list of orders and the line items which got its schedule line details changed by the rescheduling job (V_V2 batch job overnight).
I appreciate any inputs from people who found a way out using the report and got the necessary details from it.
Thanks,
Mothish babu
Edited by: B.Mothish Babu on Apr 21, 2008 11:34 AM