Dear all,

Could you please help me on finding a solution to the following request:

We would like to have a re-scheduling of all open operations in a production order. This should be done always after the confirmation of an operation (example: operation 0010 has been confirmed --> all operations after 0010 are re-scheduled based on the end-date of operation 0010).

We would like to know the End-date of the whole order in case if one operation has been done with a delay.

Thank you in advance for your help.