Hope you all are doing great. My clients has been doing create base planning object (KKE1) functionality since long. Now my clients wants to pick only material master price not the conversion cost or activity price related to that material while doing KKE1.

Kindly advise how can we achive this.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Bhaskar Basam Jan 08 at 02:54 AM
0

Hi Avinash,

You can explode the material cost estimate in BPO (Ctrl+Shift+F8) and remove the conversion cost by giving the filter criteria.

Regards

Bhaskar