on 04-21-2008 7:26 AM
Hi,
In MC94 there is a function to SETTING --> FIRMING --> SWITCH ON / SWITCH OFF.
What is its function? When we should switch on and off?
Regards
HHS
hi
it means ur plan will be firmed at this level and if u change plan at lower level and start aggregation , plan will not be changed at higher level due to firming.
Reward if useful
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.