Hi,

In MC94 there is a function to SETTING --> FIRMING --> SWITCH ON / SWITCH OFF.

What is its function? When we should switch on and off?

Regards

HHS

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

it means ur plan will be firmed at this level and if u change plan at lower level and start aggregation , plan will not be changed at higher level due to firming.