Former Member
Apr 19, 2008 at 12:15 PM

Activity Confirmation

629 Views

hi,

The scenario is as follows:

The activity (Machine activity) required to produce 1000 pc’s is 3 hrs. When partial confirmation is done through COR6N for 500 pc’s , System proposes ( By Back flush) the component quantities proportion to the confirmation quantity of 500 Pc’s but not the activity ( ie, 1.5 hrs).

Can any body tell me how to meet the above requirement?

Regards,

Raghu