on 04-19-2008 9:21 AM
While Confirming Production in MFBF , there are some items which should not be seen for material consumption . How can this be done by changing Routing material allocation.
Thanks and Regards
S.D.Dighe
Assign the material not to be seen in MFBF to a different production line. Then in MFBF select the production line as per and go ahead with component bakcflush