Dear All,

Pls explain me about the plant parameter ???

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear

Try to check the t code om18 .

Amin

Former Member
0 Kudos

Hi,

Here is few more inputs:

MRP plant parmaters are maintained in transaction OPPQ.

Order type for convertion of planned order into production order is maintained,

If order start in past allowed or not,

Bom selection,routing selection id etc are maintained.

The planning horizon period, special procurement key are also maintained here.

Plant Parameter settings are necessary to run the MRP for Plant.

Some important settings are Bom/routing selection, BOmmexplosion , planning Horz, MRP contoll , planned order .

Please check with OPPQ & get the details with F1 help.

All the settings should be "maintained" before the MRP.