on 04-19-2008 5:26 AM
hi Experts,
Where is the linking of maintenance activity to work center
is done?
my HR consultant has mapped maintenance staff
(Fitter, Electrician etc.) As employee, with employee number
Is it possible that, employee that has been mapped by HR consultant as Employee can be mapped as work center?or we have to create separately?
Please give details
Thanks and regards
hi
i think while creating the workcenter itself you can able to assign the created employee using the HR assignment
kindly check in workcenter master data
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
If you want to assign the HR objects people, positions, requirements profiles and qualifications to LO work centers, you must first assign the work center to an HR work center. This can be an existing HR work center. You can also create a new HR work center (which can have the same name as the LO work center) during the assignment procedure.
Alternatively you can assign a LO work center to an organizational unit in HR. You can then create no further links to other HR objects via the organizational unit.
For further details you can visit the Link below:
http://help.sap.com/saphelp_erp60_sp/helpdata/en/b1/c0372f439a11d189410000e829fbbd/content.htm
Hope this helps..
Regards,
Siva
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.