MD04 how can I change entry MDKP-SUM01?

Former Member
0 Kudos

Hi guys,

could someone please tell me how to change the value of the fixed receipts MDKP-SUM01?

Cheers,

Kiz

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

There are so many reciepts ( Planned independent requirements , Purchase requisitions , Purchase orders , process orders or production orders ) while processing thses orders itself you can change the qty and date , for ex. Purchase order of some " externally procured" item ( T- code ME22N ) change mode , you can change the qty and date for that order , which would be reflected in MD04

As such you cannot change it in MD04 list

its a display list of requirements and reciepts.

Former Member
0 Kudos

Hi Kiz,

MD04 is a stock/requirement list which is giving list of reciepts and requirements, say for ex. one mateial is there ( 4000736 ) whose " planning time fence " is maintained 20 days ( it can be maintained in MM record or in MRP customisation, first MM record is chosen) , and if you plan for the material today , from today upto 20 days a " FENCING" is formed , means the reciepts are firmed ( fixed ) one cannont change it s qty or date . you can only change the reciepts whihc fall outside of the " planning time fence" .

The reciepts whihc fall in " Planning time fence " only are fixed.

outside of it are not fixed.

Thanks and regards