Is it possible to chnge the Valid from date of the BOM?

If NO then what could be done to chnge the valid from date of the BOM?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can not change the valid from date to BOM.

You have to implement Engineering Change Management to apply this.

Regards,

Dharma

Former Member
0 Kudos

So, what can be done to change the date ?

i want to chnge date from 08.05.2008 to 01.01.1900

former_member335796
Active Contributor
0 Kudos

Hi Chetan,

If you want to change the BOM date then create a new Alitenative with the date new date 01.01.1900.

(you can do this by changing the date to 01.01.1900 at the time of 2nd Alternative creation)

You can use this second alternative in your subsequest steps.

Regards,

Siva

Former Member
0 Kudos

Hi,

Regarding ECM you can refer old threads.

Without ECM, you can create one alternate BOM with valid date from 01.01.1900

Regards,

Dharma

Answers (1)

Answers (1)

former_member335796
Active Contributor
0 Kudos

Hi Chetan,

It is not possible to change the valid from date of the BOM.

If you use ECM and implement Revision Level, Based on the Revision Level you can have the diffrent BOM valid from dates effective.

Regards,

Siva