Dear all

we have two plants (plant1 and plant2)

when iam creating production order for a finished product in plant1 (for which there is no BOM),through CO01, while maintaining components, if i give for some of components plant2(in place of plant1), system is accepting.Why is it?

my doubt is ,as this order is for plant1, it should accept components of plant1 only.