COR8 give message AG031: Past receipts were taken into account

Former Member
0 Kudos

Hello dears,

when I run COR8 to convert planned order in process order, the system give the message AG031:

"Past receipts were taken into account"

Do you know wkat it means?

Thanks in Advance,

Best Regards.

Juan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Juan,

you can any of the below solutions

1.

I think the problem is with respect to ATP check which the system is performing for individual and collective requirement.

so go to T_code - OVZ2 and select "No check" for 01-individ and 02 - collective.

2.

In availabilty check control - opjj

please uncheck the recipts in past check box

regards

Ramesh

Edited by: rameshbabu patnala on Apr 17, 2008 3:37 PM

Former Member
0 Kudos

Thank you,

your help has been very helpful.

sys.

Juan