on 04-17-2008 12:16 PM
Hi all ,
cal we go for capacity leveling for Planned orders .?
If yes , Pl guide how to carry out the same .
Regards
Hi Venky,
yes, u can do the capacity leveling for Planned Order same as Production order.
Only thing u have to carry out lead time scheduling . Run the MRP with lead time scheduling and dispatch the planned order at CM21.
Select the Planned order and dispatch.
Pradeep.