Hi Experts,
I would like to ask if you could kindly help me or provide me with the basic config re material staging (if there are any).
Thank you very much.
Mylene
Hi,
I am trying to give some inputs
i)Check for control cycles by LS41
ii)Create 1 new control cycle:PK05
iii)Create Control cycle : LPK1
Customization for creation of TRs for staging pick parts.
Log.exe->WM->Interfaces->Define Production ->choose PP- production view
iv) Create P.Order with Backward scheduling:
v) Display the TRs for pick parts that was created automatically by the system.
LP11 ->Select plant and Production supply Area, choose material staging.
vi)Create TO for TR
vii) Check for remaining components which are not staged as pick parts.
viii) Request one create of material.
viii)Create stock removal TRs In BG & confirm in BG.
ix)Check the Stock overview.
x)Confirm the P.Order
xi)check again the Stock Overview.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.