on 04-17-2008 7:11 AM
Hi Experts
Iam new to the Automatic reorder point process, it says that the reorder point and safety stock is calculated based on integrated forecast program, can anyone tell me how its calculating in forecast, can u give me a example.
Thanks in advance.
Regards
Rajaram
Hi,
pls find the definition for Automatic ROP from SAP help.
Automatic Reorder Point Planning
In automatic reorder point planning, both the reorder level and the safety stock level are determined by the integrated forecasting program.
The system uses past consumption data (historical data) to forecast future requirements. The system then uses these forecast values to calculate the reorder level and the safety stock level, taking the service level, which is specified by the MRP controller, and the material's replenishment lead time into account, and transfers them to the material master.
Since the forecast is carried out at regular intervals, the reorder level and the safety stock level are continually adapted to the
Regarding the inputs - Consumption Values (hist data) shd be there , MM02-Forecasting view shd be defined .
While executing the Forecast, system updates the ROP and safety stock.
Regards,
Sheik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Automatic reorder point planning works on consumption rate. If you go for manaul ROP planning, the rorder point is constant.
Some times you have decided on the last year data and this year let us say it is not used much...hence system will go for lesser reorder point value so that inventory cost will be reduced. How system will calculate - depends on consumption of that material in the period
You can see the details in the link..
http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d3f9344af11d182b40000e829fbfe/frameset.htm
pl come back if required
Regards,
Anand.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi anand
actually mrp type for automatic reorder point is VM no,
u r telling V1, then do we need to fill the reorder point and safety stock and all.
or it will fetch automatically. and we have not implemented the forcasting in our comapny, how it will work, do we have to implement it first.
pls explain me clearly yar.
Regards
Rajaram