Move costs from one Production order to more Production orders

Dec 30, 2017 at 03:59 PM

59

avatar image
Former Member

Hi,

is there a possibility to move costs from one production order to other production orders in one step?

e.g.

Order 1 will collect costs from workcenter 1 and workcenter 2

next step :

Allocate costs from Order 1 to order 2 and order 3 so that:

Order 2 ( 0,7 costs from workcenter acty 1 and 0,5 from workcenter acty 2) | Order 3 ( 0,3 from workcenter acty 1 and 0,5 from workcenter acty 2)

is there a t-code? Will Kb15n or Kb21n work?

thanks

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Muhammad Usman Akram Jan 01 at 09:05 AM
0

Dear Jan,

you cannot allocate cost from one production order to other production order via KB21N or KB15N or other cost allocation processes like distribution or assessment cycle until unless you activate KAMV transaction for KB15N in BS12 T-code.

steps are:-

  1. execute BS12 T-code
  2. select Object category e.g.for process order use ORB
  3. mark check KAMV transaction
  4. saved the configuration

for distribution or assessment please use business Transaction RKIU and RKIV

Regards