on 12-28-2017 10:41 AM
I can able to see the cost spent report from MCI8 transaction, but it shows equipment wise but I need order wise
Hi Devraj,
IW38/IW39 is also helpful to get the planned cost and actual cost reporting order/FL/Equipment wise.
Regards,
Baiju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Transaction KOB1 or KOB1N should work for this
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.