Dear all

I've changed a BOM with reference to a change number. Now, is there any way to use that old version of BOM in production planning? for example with reference to change number.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 02 at 03:08 PM

    Hello

    You can use it if you set an explosion date where this BOM was still valid.

    Regards,

    Caetano