Dear all

I've changed a BOM with reference to a change number. Now, is there any way to use that old version of BOM in production planning? for example with reference to change number.

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You can use it if you set an explosion date where this BOM was still valid.

Regards,

Caetano