Hi all,

I ned to transfer a matl from sloc to sloc for a company.

Sloc are located far away from each.

I need to send matl in between these sloc.

What r all etting reqd to acheive this including tax?

is 311 MT is alone fulfill this reqt

Becas we r having 25 storage locations in US .

matl has to be transferred based on stock avalablity

pl reply if any suggestions

thanks

We are having one common plant and assigned to 25 sloc.

A.Gururajan

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi

Use Stock Transport PO ( document type UB) to capture additinal amount ( i.e Fright, tax etc).

Thanks

Anandamurthy

Former Member
0 Kudos

You can also use MIGO Trxn code where in you have to select the option Remove from storage in drop down and a material document will be generated where in system allows you to specify target storage location and batch etc.This removed stock will be posted into Stock in Transfer.

For receiving into target storage location select Place in Storage option in the drop down of MIGO where in system asks you to enter the Matl document by which you have removed from the source storage location and the same stock which is in Stock in Transfer will be automatically adopted by the system.

By this Two step procedure you can track the material very well. Regards

csaba_szommer
Active Contributor
0 Kudos

Hi Gururajan,

Are your SLocs under the same plant (I don't think)?

If they are under different plants you cannot use MB1B +311. If the situation is not this you can use MB1B 313 & MB1B 315 (MBSU + material doc reference) to transer the goods in two step.

BR

Csaba

Sorry I wasn't careful enough > SLocs belong to one plant...

Edited by: Csaba Szommer on Apr 14, 2008 12:37 PM

Edited by: Csaba Szommer on Apr 14, 2008 12:38 PM

Former Member
0 Kudos

Hi Czesaba,

Thanks for reply

my scenarios is like these

Based on customer reqt matl will be shipped from the available sloc.

is it possible to transfer matl from onlk sloc to another when plants are different

pl reply

guru

csaba_szommer
Active Contributor
0 Kudos

Hi,

Of course it is possible to do stock transfer between plants, please check the following link:

http://help.sap.com/saphelp_46c/helpdata/en/a5/63385543a211d189410000e829fbbd/frameset.htm

Csaba

Former Member
0 Kudos

Hi,

Since all the storage loacations belongs to one Plant / Valuation area.

Use Two step stock trasfer (Mvt 313 & 315) between storage locations.

Thanks

Anandamurthy

Former Member
0 Kudos

Hi

Please try with T.code :MB1B for Transfer posting of Quantities between different storage locations if you are using any special stock mention it in the tab indicating for example q for project