diff between ms02 and md02

hello any body,

explin me what is the difference between md02 nad ms02. when we have to run these two transation codes.

bhakta

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Apr 14, 2008 at 09:12 AM

    Dear Bhakta vatsalam,

    MS02 - Long-Term Planning: Single Item,Multi Level.Where after giving the demand for a material in MD61 in an inactive version &

    assigning that particular material to a Planning scenario, LTP run will be carried out for that material.

    Simulative planned orders are obtained for that material which can be seen in MS04.

    MD02 - Single Item,Multi Level run - MRP for a material which has got PIR's in active version and we get planned orders for these

    materials which can be processed for further activities.

    Regards

    Mangalraj.S

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      In MS02 you will get planned orders. But this planned orders can not be convert to production orders. Because this is simulation run.

      With tcode MS64, you have to copy the version to demand management. After that req plan will be transferred to MD62.

      In MD02 , it is a regular process. With this also you can plan for 5 months. Planned orders can be convert to prod order.

      Regards,

      Dharma

  • Posted on Apr 14, 2008 at 09:04 AM

    Hi,

    MS02 - Single Item Multilevel Long term Planning is used for Long Term Planning scenario. This is used to create simulation orders and plan for the Annual Production Plan.

    MD02-Single Item Multi level planning an is used to run MRP and create procurement proposals.

    Thanks and regards

    Murugesan

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 14, 2008 at 09:08 AM

    Hi,

    ms02 is a simulation mode it no where affects the costing ,inventry,sales.used mainly in long term planning

    in md02 its an mrp run will be reflectd in all the above said areas.

    rds

    sandya

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 14, 2008 at 09:10 AM

    Hi,

    MD02 - Single item multi level planning run. This will use for demand created in planning table in MD61 tcode. Regular material planning.

    MS02 - Simulation run. This is useful to run Long term planning scenario.

    Long term planning scenario created by MS31 and run by MS01 or MS02. This scenario can not be run by MD02.

    Regards,

    Dharma

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.