I am doing the setup for EWM-PP integration with PMR.

I created the PSA with staging indicator-5 and control cycle with storage location.

Now i created the process order via COR1 /released but system is not generating the PMR number. while checking the log then below messages are coming

WM staging of materials executed without error Message no. LP002

WM staging of materials not completed for entire quantity

can someone tell me what could be the issue.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Dec 26, 2017 at 04:26 PM

    PSA also assigned in BOM

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 13 at 11:54 AM

    Hi Anubhav,

    Please check below steps.

    1> Product group maintained in Product( component) for single order staging as per your config ?

    2> PSA looks different with PMR and the please share the screen shot for PSA Master, PSA ?

    3> check Status Profile in Item type PCSO and check BC set for single order.

    Status Profile StatusType Status Type Inactive Ag /SCWM/PWR DAC /SCWM/PWR DBC /SCWM/PWR DBD /SCWM/PWR DBO /SCWM/PWR DCO /SCWM/PWR DGI /SCWM/PWR DMC

    Hope it is useful.

    Regards,

    G.V.Shivakkumar