Dear All,

Can we create single alternate multi level BOM for Production & subcontracting vendor(i.e.common BOM) in REM???

We want to maintain single alternate multi level BOM for both prodn & subcontractor.

Scenario is that we have subcontracting vendor who makes chassis for us & for this we have created single level BOM with alternate-2

.Now for our production we have multi level BOM with alternate -1.

For single alternate BOM on trial basis we maintin info records for subcontracting vendor with the our prodn version & manual subcontract PR is created for the chassis.

Now when PO is created one of the normal assly not exploded only its header code appears that will create problem when migo.

So my problem is how that assy code to be explode at the time of PO(code is same

Proc. type-E

Sp. proc.- Nil)???

Kindly help....

rg

Tushar

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Apr 13, 2008 at 03:44 AM

    Dear All,

    Pl.reply

    rg

    Tushar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 13, 2008 at 07:08 AM

    Hi,

    In case of a manual subcontract PO , the reason for the components not getting copied into the order may be ..........

    Hope you have created the BOM with usage 3 (universal) ,

    then Check whether you have mentioned that usage in the Selection ID and priority in OS32 .

    If it is not included there , pls do so and try again.

    Sel ID Sel Pr BOM Usage

    ie 01 1 1

    01 2 3

    Hope it will work.

    Regards,

    Sheik

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 13, 2008 at 07:30 AM

    Hi,

    One BOM

    If you want to maintain a single BOM for inhouse production & subcontracting , then pls try as follows.

    1. Maintain spl Proc type 30

    2. Maintain Info record etc ...relevant to ext proc.

    3. Run MRP with Create Pur req indicator - 3 (planned orders)

    MRP will generate a planned order with special procurement Subcontracting.

    If you want to subcontract , then convert this planned order into a purchase requisition with item category L , from MD04 or MD14/MD15.

    If you want to produce inhouse, then convert this planned order into Production order in CO40/CO41.

    Regards,

    Sheik

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 13, 2008 at 08:51 AM

    Dear sheik,

    Thanx for your efforts.....

    But we have REM so no production order.

    Can u advice otherelse???

    rg

    Tushar

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      In REM , we cant do Backflush in MFBF with reference to this planned order.

      It throws an error: Planned order xxxx not suitable for REM

      (Since the order type of Planned order is Standard PO with spl proc subcontracting)

      So I think , there is no possibility of maintaining one BOM and you have to go for 2 BOMs.

      Have you tried mapping the BOM Usage with selection id & pls getback whether the assembly is exploded in your PO & your problem is solved r not?

      Regards,

      Sheik

  • author's profile photo Former Member
    Former Member
    Posted on Apr 13, 2008 at 02:01 PM

    Hi

    Your requirement can be met. Please give me details of Chasis material type, material grp, mrp type u r using and any other bom details.

    I can send u the solution

    Nanduri

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 14, 2008 at 06:14 AM

    Dear Nanduri,

    The header code of the HALB is same for subcontract vendor & our self same, say 'X'.

    mrp type --PD

    material group-SKD

    Proc. type -E.

    we have two alt. BOMs with alt.1 for ourself & 2 for vendor.

    Inorder to simplify BOM maintenance, we want single alt. BOM.For that we have maintain info record with our Prodn version links to alt. BOM 1 & accordingly subcontract PR & PO created.

    But in PO one of the assy code say 'Y'(Part of X) not exploded which is not phantom with Proc. type E(Note-For vendor BOM, Y with different code with phantom & proc. type is E).

    So we want this Y code(Our BOM) to exploded in PO inorder to maintain single alt. BOM to simplify maintenance.

    Kindly advice......

    rg

    Tushar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.