Skip to Content
avatar image
Former Member

Schedule plan configuration

Morning,

I would like to know if its possible to froze the generation of the fixed delivery schedules for 15 days period?

I mean: If i have a fixed delivery schedule for 05.01.2018, and if the MRP generates a new one on 01.08.2017, for 05.01.2018 is it possible to avoid it and generate a purchase requisition?

Regards

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 27, 2017 at 06:08 AM

    Hi,

    Probably check the concept of planning time fence.

    Regards,

    Sundaresan.K

    Add comment
    10|10000 characters needed characters exceeded