Schedule plan configuration

Dec 22, 2017 at 11:26 AM

31

avatar image
Former Member

Morning,

I would like to know if its possible to froze the generation of the fixed delivery schedules for 15 days period?

I mean: If i have a fixed delivery schedule for 05.01.2018, and if the MRP generates a new one on 01.08.2017, for 05.01.2018 is it possible to avoid it and generate a purchase requisition?

Regards

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

KRISHNAMOORTHY SUNDARESAN Dec 27, 2017 at 06:08 AM
0

Hi,

Probably check the concept of planning time fence.

Regards,

Sundaresan.K